Key Learning Outcomes

  • Place scaffold bay lines directly over as-built scan data using ScaffPlan inside SketchUp.
  • Derive accurate bay widths from real site measurements using point cloud data.
  • Use Clip Box and inspection tools in Trimble Scan Essentials to isolate constraints and analyse clearances.
  • Perform clash detection using Inspection Map with defined distance tolerances.
  • Optimise bay widths to resolve clashes with trees, fencing, and fixed obstacles.
  • Modify multiple bays efficiently using controlled parameter selection (untick all → change specific parameter only).
  • Strategically plan scaffold access (stairs and ladders) based on real site restrictions.
  • Calculate correct top working platform heights from measured scan data.
  • Adjust scaffold geometry to suit balcony undersides and façade variations.
  • Use Neighbor Bay Adjustment for parametric clash resolution without rebuilding geometry.